1 |
Filing – Applicant files application, pays any required fee, and provides
landowner notice. Applicant may meet with DEQ staff prior to this. |
|
|
2A |
Notice of filing – Applicant publishes notice in one newspaper local to site. |
|
|
2B |
Process meeting – Notice – 30-day opportunity is published with notice
of filing. DEQ holds meeting if requested and sufficient interest is shown. |
|
|
3 |
Administrative completeness review – DEQ reviews application and
asks applicant to supply any missing information. |
|
|
4 |
Technical review – DEQ reviews application for technical compliance
and requests applicant to cure any deficiencies. |
|
|
5 |
Draft permit or draft denial – DEQ prepares this after completing review. |
|
|
6A |
Notice of draft permit, public comment period and public meeting request
opportunity – Applicant publishes this in one newspaper local to site
(DEQ publishes notice of draft denial). Public comment period – 45 days for hazardous waste draft permits; 30 days for all others. |
|
|
6B |
Public meeting – Conducted by DEQ if held. The applicant or a
representative of the applicant shall be present at the meeting to respond
to questions. |
|
|
7A |
Review of comments – DEQ (written response) |
|
|
7B |
Notice of proposed permit – Applicant publishes, in one newspaper
local to site, notice of 20-day opportunity to review permit and request
administrative hearing. |
|
|
7C |
Administrative permit hearing – Conducted by DEQ if held.
Results in final order. |
|
|
8 |
Issuance or denial – DEQ’s final decision. |